Posted by SCRUMstudy® on April 30, 2024
Categories: Agile Product Backlog SBOK® Guide Scrum Scrum Guide
In Scrum, Scrum Sprint Planning involves essential steps to ensure clarity and alignment within the Scrum Team. It begins with the Product Owner explaining the highest-priority items from the Product Backlog to the team. During this collaborative session, the team discusses and understands these items thoroughly. They then collectively decide on the Sprint Goal, which serves as the objective for the upcoming Sprint. Subsequently, the team breaks down the selected Product Backlog items into smaller tasks and estimates the effort required for each task. By the end of Sprint Planning, the Scrum Team has a well-defined Sprint Backlog containing the selected Product Backlog items, tasks, and their estimated effort, ready to begin work on achieving the Sprint Goal. This structured approach ensures that the team is aligned with the project objectives and equipped to deliver value incrementally during the Sprint..
Based on the Guide to Scrum Body of Knowledge (SBOK Guide), it is time-boxed to eight hours for a one-month Sprint and is divided into two parts – Objective Definition and Task Estimation.
1. Objective Definition—during the first half of the meeting, the Product Owner explains the highest priority User Stories or requirements in the Prioritized Product Backlog to the Scrum Team. The Scrum Team in collaboration with the Product Owner then defines the Sprint goal.
2. Task Estimation—during the second half of the meeting, the Scrum Team decides “how” to complete the selected Prioritized Product Backlog Items to fulfil the Sprint goal.
During Sprint Planning Meetings, the User Stories, which are approved, estimated, and committed are taken up for discussion. Each Scrum Team member does a quick estimation of tasks using tools such as planning poker. If the discussions start taking more time, it would mean that the User stories were not completely ready to be taken up for the sprint. Each Scrum Team member also uses Effort Estimated Task List to select the tasks they plan to work on in the Sprint, based on their skills and experience. The team reaches a consensus about the amount of work that needs to be put in this sprint. The Scrum Team also creates the Sprint Backlog and Sprint Burndown Chart using the User Stories and the Effort Estimated Task List during the Sprint Planning Meetings. The team can give a verbal commitment to complete the tasks planned for the sprint.
Try to avoid doing the following tasks during the meeting. They help you with preparation and should be prepared before the start of the meeting.
Refining: Refining helps ensure that there is a clarification of requirements and their User Stories. Its done in advance of the Sprint Planning Meeting so that the team has a well-analyzed and clearly defined set of stories that can be easily broken down into tasks and subsequently estimated.
Updates/Revisions: Updates can include revisions to the original User Story estimates based on task creation and complexity factors discussed during the Sprint Planning Meeting.
The bottom line is that if you follow these points, you will be able to do effective planning without spending a lot of time.
Posted by SCRUMstudy® on March 27, 2024
Categories: Agile SBOK® Guide Scrum Sprint Sprint Backlog
Scrum Sprint Planning is a pivotal event in the Scrum framework, meticulously designed to set the stage for successful project execution. As outlined in the SBOK guide, Sprint Planning involves collaborative efforts among the Scrum Team members to define the objectives for the upcoming Sprint and devise a clear plan of action to achieve them. During this time-boxed session, typically lasting up to two hours for every week of Sprint duration, the Product Owner presents the highest priority User Stories from the Prioritized Product Backlog to the team. Together, the Scrum Team commits to these User Stories, collectively determining how they will be transformed into shippable product functionalities. This commitment forms the basis of the Sprint Backlog, where the selected User Stories and their corresponding tasks are documented and tracked throughout the Sprint.
In a Scrum project, every sprint begins with Sprint Planning Meeting. The main objective should only be planning the sprint. Ensure that the meeting is attended by the all team members including the Product Owner, Scrum Master and the Scrum Team. You can also include part time resources for this meeting. This provides an important opportunity for the Scrum Team to select how much work they can do in the coming sprint.
Based on the Guide to Scrum Body of Knowledge (SBOK Guide), it is time-boxed to eight hours for a one-month Sprint and is divided into two parts – Objective Definition and Task Estimation.
1. Objective Definition—during the first half of the meeting, the Product Owner explains the highest priority User Stories or requirements in the Prioritized Product Backlog to the Scrum Team. The Scrum Team in collaboration with the Product Owner then defines the Sprint goal.
2. Task Estimation—during the second half of the meeting, the Scrum Team decides “how” to complete the selected Prioritized Product Backlog Items to fulfil the Sprint goal.
During Sprint Planning Meetings, the User Stories, which are approved, estimated, and committed are taken up for discussion. Each Scrum Team member does a quick estimation of tasks using tools such as planning poker. If the discussions start taking more time, it would mean that the User stories were not completely ready to be taken up for the sprint. Each Scrum Team member also uses Effort Estimated Task List to select the tasks they plan to work on in the Sprint, based on their skills and experience. The team reaches a consensus about the amount of work that need to put in this sprint. The Scrum Team also creates the Sprint Backlog and Sprint Burndown Chart using the User Stories and the Effort Estimated Task List during the Sprint Planning Meetings. The team can give a verbal commitment to complete the tasks planned for the sprint.
Try to avoid doing the following tasks during the meeting. They help you for preparation and should be prepared before the start of the meeting.
Refining: It helps ensure that refining of requirements and their User Stories is done well in advance of the Sprint Planning Meeting so that the team has a well-analyzed and clearly defined set of stories that can be easily broken down into tasks and subsequently estimated.
Updates/Revisions: Updates can include revisions to the original User Story estimates based on tasks creation and complexity factors discussed during the Sprint Planning Meeting.
Bottom line is that if you follow these points, you will be able to do effective planning without spending a lot of time.
Posted by SCRUMstudy® on March 26, 2024
Categories: Agile SBOK® Guide Scrum Sprint Sprint Backlog
Scrum Sprint Planning is a crucial event within the Scrum framework where the Scrum Team collaborates to define the work to be accomplished during the upcoming sprint. Facilitated by the Scrum Master, this meeting involves the entire Scrum Team, including the Product Owner and Development Team. During Sprint Planning, the team reviews the Product Backlog, discusses the sprint goal, and selects high-priority items that can be realistically completed within the sprint. The result is a clear and actionable Sprint Backlog that guides the team's efforts, ensuring alignment and focus on delivering valuable increments of the product. Effective Sprint Planning fosters communication, commitment, and a shared understanding of the work ahead.
In a Scrum project, every sprint begins with a Sprint Planning Meeting. The main objective should only be planning the sprint. Ensure that the meeting is attended by all team members including the Product Owner, Scrum Master, and the Scrum Team. You can also include part-time resources for this meeting. This provides an important opportunity for the Scrum Team to select how much work they can do in the coming sprint.
Based on the Guide to Scrum Body of Knowledge (SBOK Guide), it is time-boxed to eight hours for a one-month Sprint and is divided into two parts – Objective Definition and Task Estimation.
1. Objective Definition—during the first half of the meeting, the Product Owner explains the highest priority User Stories or requirements in the Prioritized Product Backlog to the Scrum Team. The Scrum Team in collaboration with the Product Owner then defines the Sprint goal.
2. Task Estimation—during the second half of the meeting, the Scrum Team decides “how” to complete the selected Prioritized Product Backlog Items to fulfill the Sprint goal.
During Sprint Planning Meetings, the User Stories, which are approved, estimated, and committed are taken up for discussion. Each Scrum Team member does a quick estimation of tasks using tools such as planning poker. If the discussions start taking more time, it would mean that the User stories were not completely ready to be taken up for the sprint. Each Scrum Team member also uses the Effort Estimated Task List to select the tasks they plan to work on in the Sprint, based on their skills and experience. The team reaches a consensus about the amount of work that needs to be put in this sprint. The Scrum Team also creates the Sprint Backlog and Sprint Burndown Chart using the User Stories and the Effort Estimated Task List during the Sprint Planning Meetings. The team can give a verbal commitment to complete the tasks planned for the sprint.
Try to avoid doing the following tasks during the meeting. They help you with preparation and should be prepared before the start of the meeting.
Refining: It helps ensure that refining of requirements and their User Stories is done well in advance of the Sprint Planning Meeting so that the team has a well-analyzed and clearly defined set of stories that can be easily broken down into tasks and subsequently estimated.
Updates/Revisions: Updates can include revisions to the original User Story estimates based on task creation and complexity factors discussed during the Sprint Planning Meeting.
The bottom line is that if you follow these points, you will be able to do effective planning without spending a lot of time.
Posted by SCRUMstudy® on February 09, 2024
Categories: Agile SBOK® Guide Scrum Scrum Guide Scrum Team
Scrum Sprint Planning is a pivotal event in Agile methodology where the Scrum Team collaborates to determine the work to be performed during the upcoming Sprint. This meeting involves the Product Owner presenting the highest-priority User Stories from the Prioritized Product Backlog. The team then discusses and commits to these User Stories, breaking them down into actionable tasks. Sprint Planning ensures that the team is aligned on the Sprint goals, understands the scope of work, and is prepared to deliver valuable increments by the Sprint's end. This structured planning session fosters clear communication, sets expectations, and lays a solid foundation for Sprint's success.
One of the questions that throw a curveball into the diligent efforts of the Scrum community to introduce the Scrum Framework is:
How long should it be?
Why should there be a fixed length for Sprints?
After all, Scrum is about adapting to change; poorly chosen Sprint length will lead to impatient management, an overburdened Scrum Team, and ultimately, bad Project output. Variable Sprint Length seems like a magic bullet that will enable work according to the Real word conditions as expected now rather than anticipated for later. Sprint planning now becomes easier. One does not have to overanalyze whether to include or exclude one more week which will bring the Product to a better Stage after every Sprint but make the process less flexible. Why are we not seeing more Vari-time Sprinting?
The primary reason why we do not have this is because of two words: Time-Boxing. It is a principle of Scrum where that proposes fixing a certain amount of time for each process and activity in a Scrum project (Source: SBOK). It Brings Discipline. In Scrum, Instead of filling pages of Forms and Progress reports, the Scrum team members can avoid Status Meetings and focus on working. The cost of doing that is the Discipline of time-boxing. So the Middle Management guys know that they will get timely data to do their number crunching without bothering the Project team. Timely Feedback and Status reports can be sent to external Clients who will then slowly release the next installment of payment.
Now that we have established that a Fixed Sprint length is necessary, what is the Ideal Length?
The Simple Trite Answer is “It Depends”, but on what? Some factors are the size of the Company, how much testing is required, the amount of “Creativity” required, and the nature of clarity and change in the project. Larger organizations have a greater need for Documentation (so all relevant people know what is happening) and longer-term planning thus necessitating longer Sprint Lengths. Early-stage startups should have short Sprint Lengths as they need to accelerate their learning curves and adapt their offering to fit what the market wants. Everyone already knows what is happening in the organization and the project could be dead by next financial year if the offering is not refined this week. Creativity requires time to come up with an Idea and not the rush of deadline looming. Stable project parameters allow for longer Sprints of 4 to 6 weeks. If project requirements are themselves not clear, shorter Sprints of 1 to 4 weeks are warranted.
Ultimately, however, the most important question is: what is the Scrum Team comfortable with? This brings us to another important Principle: Self-Organization. The Team should buy in and say: “We are going to have X week Sprint” Let the Scrum team members do the above analysis themselves and come up with a Sprint Length without pushing it on them.
Posted by SCRUMstudy® on February 06, 2024
Categories: Agile Product Backlog SBOK® Guide Scrum Scrum Guide
In Scrum, the Sprint Planning Meeting is crucial for setting the stage for the upcoming sprint. According to SCRUMstudy, this meeting involves the entire Scrum Team and is primarily facilitated by the Scrum Master. During this session, the Product Owner presents the prioritized backlog items, and the team collaborates to define the sprint goal and select the user stories they commit to completing. The team then breaks down these stories into tasks and estimates the effort required for each. This collaborative process ensures that everyone has a clear understanding of the work ahead, aligns on the sprint objectives, and feels a sense of ownership over the sprint plan.
Based on the Guide to Scrum Body of Knowledge (SBOK Guide), it is time-boxed to eight hours for a one-month Sprint and is divided into two parts – Objective Definition and Task Estimation.
1. Objective Definition—during the first half of the meeting, the Product Owner explains the highest priority User Stories or requirements in the Prioritized Product Backlog to the Scrum Team. The Scrum Team in collaboration with the Product Owner then defines the Sprint goal.
2. Task Estimation—during the second half of the meeting, the Scrum Team decides “how” to complete the selected Prioritized Product Backlog Items to fulfil the Sprint goal.
During Sprint Planning Meetings, the User Stories, which are approved, estimated, and committed are taken up for discussion. Each Scrum Team member does a quick estimation of tasks using tools such as planning poker. If the discussions start taking more time, it would mean that the User stories were not completely ready to be taken up for the sprint. Each Scrum Team member also uses Effort Estimated Task List to select the tasks they plan to work on in the Sprint, based on their skills and experience. The team reaches a consensus about the amount of work that needs to be put in this sprint. The Scrum Team also creates the Sprint Backlog and Sprint Burndown Chart using the User Stories and the Effort Estimated Task List during the Sprint Planning Meetings. The team can give a verbal commitment to complete the tasks planned for the sprint.
Try to avoid doing the following tasks during the meeting. They help you with preparation and should be prepared before the start of the meeting.
Refining: Refining helps ensure that there is a clarification of requirements and their User Stories. Its done in advance of the Sprint Planning Meeting so that the team has a well-analyzed and clearly defined set of stories that can be easily broken down into tasks and subsequently estimated.
Updates/Revisions: Updates can include revisions to the original User Story estimates based on task creation and complexity factors discussed during the Sprint Planning Meeting.
The bottom line is that if you follow these points, you will be able to do effective planning without spending a lot of time.
Posted by SCRUMstudy® on January 18, 2024
Categories: Agile SBOK® Guide Scrum Scrum Guide Scrum Team
O Scrum Sprint Planning é um evento essencial na metodologia Agile, onde a Equipe Scrum colabora para determinar o trabalho a ser realizado durante o próximo Sprint. Esta reunião envolve o Product Owner apresentando as User Stories de maior prioridade do Prioritized Product Backlog. A equipe então discute e se compromete com essas User Stories, dividindo-as em tarefas acionáveis. O Sprint Planning garante que a equipe esteja alinhada com as metas do Sprint, entenda o escopo do trabalho e esteja preparada para entregar incrementos valiosos até o final do Sprint. Esta sessão de planejamento estruturada promove uma comunicação clara, define expectativas e estabelece uma base sólida para o sucesso do Sprint.
Uma das perguntas que joga uma bola curva nos esforços diligentes da comunidade Scrum para introduzir o Scrum Framework é:
Qual deve ser a duração?
Por que deve haver uma duração fixa para os Sprints?
Afinal, o Scrum é sobre adaptação à mudança; uma duração de Sprint mal escolhida levará a uma gestão impaciente, uma Equipe Scrum sobrecarregada e, finalmente, a uma saída ruim do Projeto. O comprimento variável do sprint parece uma bala mágica que permitirá o trabalho de acordo com as condições reais do mundo, conforme esperado agora, em vez de antecipado para mais tarde. O planejamento do sprint agora se torna mais fácil. Não é preciso analisar demais se deve incluir ou excluir mais uma semana, o que levará o produto a um estágio melhor após cada sprint, mas tornará o processo menos flexível. Por que não estamos vendo mais sprints de tempo variável?
A principal razão pela qual não temos isso é por causa de duas palavras: Time-Boxing. É um princípio do Scrum que propõe fixar uma certa quantidade de tempo para cada processo e atividade em um projeto Scrum (Fonte: SBOK). Traz disciplina. No Scrum, em vez de preencher páginas de formulários e relatórios de progresso, os membros da equipe Scrum podem evitar reuniões de status e se concentrar no trabalho. O custo de fazer isso é a disciplina do time-boxing. Portanto, os caras da gerência intermediária sabem que obterão dados oportunos para fazer seus cálculos numéricos sem incomodar a equipe do projeto. Relatórios de feedback e status oportunos podem ser enviados para clientes externos que, então, liberarão lentamente a próxima parcela do pagamento.
Agora que estabelecemos que uma duração de sprint fixa é necessária, qual é a duração ideal?
A resposta simples e banal é "Depende", mas de quê? Alguns fatores são o tamanho da empresa, quantos testes são necessários, a quantidade de "criatividade" necessária e a natureza da clareza e mudança no projeto. Organizações maiores têm uma necessidade maior de documentação (para que todas as pessoas relevantes saibam o que está acontecendo) e planejamento de longo prazo, necessitando, portanto, de durações de sprint mais longas. Startups em estágio inicial devem ter durações de sprint curtas, pois precisam acelerar suas curvas de aprendizado e adaptar sua oferta para se adequar ao que o mercado deseja. Todos já sabem o que está acontecendo na organização e o projeto pode estar morto no próximo ano fiscal se a oferta não for refinada esta semana. A criatividade requer tempo para surgir uma ideia e não a pressa do prazo iminente. Parâmetros de projeto estáveis ??permitem sprints mais longos de 4 a 6 semanas. Se os requisitos do projeto não estiverem claros, Sprints mais curtos de 1 a 4 semanas são garantidos.
No final das contas, no entanto, a pergunta mais importante é: com o que o Time Scrum se sente confortável? Isso nos leva a outro Princípio importante: Auto-Organização. O Time deve comprar e dizer: "Vamos ter um Sprint de X semanas". Deixe que os membros do time Scrum façam a análise acima eles mesmos e criem uma Duração do Sprint sem forçá-los.
Posted by SCRUMstudy® on September 20, 2023
Categories: Agile SBOK® Guide Scrum Scrum Guide Scrum Team
Scrum Sprint Planning is a pivotal event in Agile methodology where the Scrum Team collaborates to determine the work to be performed during the upcoming Sprint. This meeting involves the Product Owner presenting the highest-priority User Stories from the Prioritized Product Backlog. The team then discusses and commits to these User Stories, breaking them down into actionable tasks. Sprint Planning ensures that the team is aligned on the Sprint goals, understands the scope of work, and is prepared to deliver valuable increments by the Sprint's end. This structured planning session fosters clear communication, sets expectations, and lays a solid foundation for Sprint's success.
One of the questions that throw a curveball into the diligent efforts of the Scrum community to introduce the Scrum Framework is:
How long should it be?
Why should there be a fixed length for Sprints?
After all, Scrum is about adapting to change; poorly chosen Sprint length will lead to impatient management, an overburdened Scrum Team, and ultimately, bad Project output. Variable Sprint Length seems like a magic bullet that will enable work according to the Real word conditions as expected now rather than anticipated for later. Sprint planning now becomes easier. One does not have to overanalyze whether to include or exclude one more week which will bring the Product to a better Stage after every Sprint but make the process less flexible. Why are we not seeing more Vari-time Sprinting?
The primary reason why we do not have this is because of two words: Time-Boxing. It is a principle of Scrum where that proposes fixing a certain amount of time for each process and activity in a Scrum project (Source: SBOK). It Brings Discipline. In Scrum, Instead of filling pages of Forms and Progress reports, the Scrum team members can avoid Status Meetings and focus on working. The cost of doing that is the Discipline of time-boxing. So the Middle Management guys know that they will get timely data to do their number crunching without bothering the Project team. Timely Feedback and Status reports can be sent to external Clients who will then slowly release the next installment of payment.
Now that we have established that a Fixed Sprint length is necessary, what is the Ideal Length?
The Simple Trite Answer is “It Depends”, but on what? Some factors are the size of the Company, how much testing is required, the amount of “Creativity” required, and the nature of clarity and change in the project. Larger organizations have a greater need for Documentation (so all relevant people know what is happening) and longer-term planning thus necessitating longer Sprint Lengths. Early-stage startups should have short Sprint Lengths as they need to accelerate their learning curves and adapt their offering to fit what the market wants. Everyone already knows what is happening in the organization and the project could be dead by next financial year if the offering is not refined this week. Creativity requires time to come up with an Idea and not the rush of deadline looming. Stable project parameters allow for longer Sprints of 4 to 6 weeks. If project requirements are themselves not clear, shorter Sprints of 1 to 4 weeks are warranted.
Ultimately, however, the most important question is: what is the Scrum Team comfortable with? This brings us to another important Principle: Self-Organization. The Team should buy in and say: “We are going to have X week Sprint” Let the Scrum team members do the above analysis themselves and come up with a Sprint Length without pushing it on them.
Posted by SCRUMstudy® on December 20, 2022
Categories: Agile Product Backlog SBOK® Guide Scrum Scrum Guide
In the world of Agile project management, the Scrum sprint planning meeting stands as a pivotal event, meticulously laying the groundwork for success. Lasting typically up to eight hours for a month-long sprint, this collaborative session involves the Scrum Team and Product Owner. It's a time to outline sprint goals, prioritize the backlog, and determine tasks. By fostering transparency and shared understanding, the meeting sets the stage for efficient sprint execution. Key outcomes include a sprint backlog detailing tasks, responsibilities assigned, and a clear path forward. Ultimately, it aligns the team's efforts with stakeholder expectations, driving iterative progress and delivering value.
Based on the Guide to Scrum Body of Knowledge (SBOK Guide), it is time-boxed to eight hours for a one-month Sprint and is divided into two parts – Objective Definition and Task Estimation.
1. Objective Definition—during the first half of the meeting, the Product Owner explains the highest priority User Stories or requirements in the Prioritized Product Backlog to the Scrum Team. The Scrum Team in collaboration with the Product Owner then defines the Sprint goal.
2. Task Estimation—during the second half of the meeting, the Scrum Team decides “how” to complete the selected Prioritized Product Backlog Items to fulfil the Sprint goal.
During Sprint Planning Meetings, the User Stories, which are approved, estimated, and committed are taken up for discussion. Each Scrum Team member does a quick estimation of tasks using tools such as planning poker. If the discussions start taking more time, it would mean that the User stories were not completely ready to be taken up for the sprint. Each Scrum Team member also uses Effort Estimated Task List to select the tasks they plan to work on in the Sprint, based on their skills and experience. The team reaches a consensus about the amount of work that needs to be put in this sprint. The Scrum Team also creates the Sprint Backlog and Sprint Burndown Chart using the User Stories and the Effort Estimated Task List during the Sprint Planning Meetings. The team can give a verbal commitment to complete the tasks planned for the sprint.
Try to avoid doing the following tasks during the meeting. They help you with preparation and should be prepared before the start of the meeting.
Refining: Refining helps ensure that there is a clarification of requirements and their User Stories. Its done in advance of the Sprint Planning Meeting so that the team has a well-analyzed and clearly defined set of stories that can be easily broken down into tasks and subsequently estimated.
Updates/Revisions: Updates can include revisions to the original User Story estimates based on task creation and complexity factors discussed during the Sprint Planning Meeting.
The bottom line is that if you follow these points, you will be able to do effective planning without spending a lot of time.
Posted by SCRUMstudy® on May 19, 2021
Categories: Product Backlog Product Owner Release Scrum Scrum Team
The Agile Scrum sprint planning meeting is a crucial event where the Scrum team collaborates to define the work for the upcoming sprint. Facilitated by the Scrum Master, this meeting involves the Product Owner presenting the prioritized backlog items, which the team then discusses and selects based on their capacity. The team breaks down these items into tasks, estimating the effort required for each. Clear sprint goals are established, ensuring everyone understands the objectives. This meeting fosters alignment, sets realistic expectations, and enhances team commitment, laying the groundwork for a focused and productive sprint cycle.
Core Principles of the Scrum Framework
Scrum is built on three pillars: transparency, inspection, and adaptation. These principles ensure that every aspect of the process is visible to those responsible for the outcome, is regularly reviewed, and can be adjusted as necessary. The framework divides the project into small, manageable segments called "sprints," typically lasting two to four weeks. This approach allows teams to deliver functional components incrementally and continuously improve based on feedback.
Scrum defines specific roles to ensure the project remains on track:
Scrum employs several artifacts and ceremonies to maintain focus and ensure effective communication:
Adopting the Scrum framework can lead to several significant benefits:
The Agile Scrum framework offers a robust and adaptive approach to project management, promoting efficiency and collaboration. By embracing its principles and practices, organizations can achieve higher quality outcomes and greater satisfaction among stakeholders.